Track 20060228
Tuesday, February 28, 2006
Monday, February 27, 2006
Sunday, February 26, 2006
Weekend Closure 1: Day 2
4:15pm demolition views from Rockwell and south alley...11:45am demolition views from south alley...
Photos From Others
Submitted by Leslie Kniskern (lkniskern@sbcglobal.net):Here are some shots I took of GRO's Sunset Ride from the Old Rockwell Station on February 19, 2006.
One more shot from the Sunset Ride. Two photos from Friday evening, February 24, 2006 - when Rockwell was full of construction trucks... and the building permit.
Finally, "If you see this" (parking meter at zero), and you suspect it's a contractor vehicle (vest in front seat) contact the FHP Tectonics Field Office at 773-308-7378 or (773-308-SERV) and ask that the vehicle be moved. UNLESS there is a sign posted that the space is reserved by a permit.
Plus two shots preparing to remove the platform canopy on Sunday morning, February 26, 2006. Residents were treated to sawzall noise as the sections were cut apart.
Saturday, February 25, 2006
Weekend Closure 1: Day 1
Feb 25 10am: view from station entrance.
Feb 25 2:30pm: view from south alley.
Friday, February 24, 2006
Thursday, February 23, 2006
Feb 23 Status
The station's still standing. The first 54-hour CTA work period at Rockwell starts at 8pm tomorrow and runs until 2am Monday, Feb 27. Demolition is scheduled to begin this weekend according to page 11 of the CTA's project update PDF document.tangent: horner park this morning.